Compare Construction Contractor Quotes
Two contractors quote for the same office floor. Check who pays for removal, materials, installation and disposal, then agree on what you’ll inspect before each payment.
Suppose you’re replacing 100 square metres of office flooring. Both contractors quote for removing the old floor and fitting the same new product. Team A includes waste disposal. Team B expects you to pay the haulier separately. Ask each team to mark its scope on the same plan, then add the separate disposal charge to Team B’s quote before comparing totals.
What to Give Each Contractor
Send each team the same dated or numbered drawing, photos of the existing space, a list of finishes to keep and the hours when crews can work. If the office on the next floor will stay open, show the route for removing debris. Agree on lift access and who will protect the building while moving materials.
A brief for an office floor
“Replace the flooring in the shaded area. Price removal, disposal, subfloor preparation, installation and refitting the existing skirting separately. If lifting the floor reveals damp or a difference in level, show us where and tell us the extra cost and time before proceeding.”
When asking for references, choose a project with similar constraints. If your office must stay open, ask who supervised the previous job, who will supervise yours and how the team handed each room back to staff.
Read the Bill of Quantities
A bill of quantities (BOQ) lists work items, quantities and prices. Pick the flooring line and locate it on the drawing. Which rooms does it cover, and how many square metres? For a lump-sum quote, have the contractor list what the price covers and what you’ll pay for separately.
| Item | What to look for | What to confirm |
|---|---|---|
| Quantities and units | Flooring is measured in square metres. Skirting in the same room is measured in linear metres. | Ask the contractor to mark the floor area and skirting runs. Record the drawing revision used for the quantities or the date the team measured on site. |
| Materials and labour | Look for the product name, size, finish, supply price and installation cost. Check accessories such as adhesive and edge trims. | If you buy the flooring, check which accessories the contractor will still supply. Agree on who will receive the delivery, count the materials and store them. |
| Before and after installation | Check removal, disposal, levelling, protection of existing finishes and cleaning before the room reopens. | Ask whether the quote covers both lifting the flooring and taking the debris away. If you must hire the haulier, add that cost to your comparison. |
| Work uncovered during removal | The area of damaged subfloor may only become clear once the finish is lifted. Ask for a unit and a repair rate. | Who will measure the damage, confirm the quantity and approve the repair price before the team proceeds? |
Team A’s BOQ example. New flooring supplied and installed: 100 m² × THB 750/m² = THB 75,000. This illustrative price covers the new floor. Team A lists removal and disposal as two separate items.
Before Ordering Flooring or Closing the Ceiling


Compare the Full Cost
In this example, both teams quote for the same 100 m² of office space, the same flooring product and the same removal and installation work. The difference is who pays for disposal. All figures are before tax.
Team A includes disposal
Total cost to owner before taxTHB 92,000Team A quotes THB 12,000 to remove the old flooring, THB 5,000 for disposal and THB 75,000 to supply and install the new floor.
Team B excludes disposal
Total cost to owner before taxTHB 95,000Team B quotes THB 88,000 for removal and the new floor. The owner pays the haulier another THB 7,000, bringing the total to THB 88,000 + 7,000 = 95,000.
On paper, Team B’s quote is THB 4,000 lower. Including disposal brings its total to THB 95,000, making Team A cheaper by THB 3,000. Compare the handover dates and arrangements for fixing defects as well. If removal reveals a damaged subfloor, ask for the repair area, extra cost and revised handover date before authorising the work.
Tie Payments to Inspections
For each payment, identify the room, the drawing revision and who will inspect the work. For a meeting room floor, check the flooring and edges against the plan, open and close the door to check clearance, and confirm the debris has been removed. The owner and contractor can then record what passed, what needs attention and when to inspect again. Use that record when releasing payment under the agreed terms.
Example inspection note. Meeting Room A, entrance door: one section of skirting is missing, as shown in the attached photo. Team A’s supervisor will arrange to fit it. Reinspection is booked for 20 June. Check that the skirting reaches the door frame and the door swings clear. Enter the actual inspection date and result against this same item.
When the owner requests extra work
Missing skirting shown on the agreed plan belongs on the defects list. An extra power socket requested later is a change. Have the contractor mark its position and price the materials, labour, opening the wall and making good the finish. Confirm the handover date and have both parties’ authorised representatives approve the price and timing before work starts.
At handover, collect the as-built drawings, test results for systems within scope, manuals and warranty terms. Record when each warranty starts, who receives a service request and how to book an inspection. Keep the details together for the person who will manage the building.
Before You Hire a Contractor
Can I ask for a quote without detailed drawings?
Yes. For a budget estimate, give each contractor the floor area, site photos and material samples. Ask what area and product the estimate assumes and whether it includes removal and disposal. Before choosing a contractor, issue the same drawings and scope to everyone and have uncertain quantities measured.
How does a lump sum differ from a unit rate?
A lump sum covers an agreed scope. A unit-rate payment uses the agreed price multiplied by the quantity measured and confirmed. A BOQ might show 100 m² × THB 750/m² = THB 75,000 for flooring and installation. Ask whether that line explains a fixed price or whether the finished floor will be measured for payment. Agree on who will measure it.
What if I buy the materials myself?
Agree on who calculates the quantity, including cuts and breakage, when delivery is due, who checks the goods and who moves them to the room. If the wrong product arrives or a box is damaged, name the person who will photograph it, count the replacements and contact the supplier. Identify who will arrange a joint inspection if a problem appears after installation.
How should I record unfinished work at handover?
Give each item a location, a dated photo, a person responsible and a repair date. Record the reinspection appointment separately. For the missing skirting in Meeting Room A, 20 June is the appointment. At the visit, record the actual date, whether the skirting reaches the frame and whether the door clears it. Mark the item as passed or still open, and set a new date if needed.