PEB Steel Structures for Warehouses

Will a column block a forklift turn? Is there enough overhead clearance to place a loaded pallet on the highest rack level? Check the drawings first, then compare what each quote covers for steelwork, delivery and erection.

In a pre-engineered building (PEB), an engineer designs the columns, rafters and secondary framing for the building’s intended use. The steelwork is fabricated off site and assembled on site. Start with the rack layout and forklift routes. If an internal column could sit along a rack row, ask for two layouts: one with internal columns and one with a clear span. Compare how many pallets each layout can accommodate and how much each option costs. Where a column might obstruct a turn or a machinery move, ask the designer to mark the narrowest point on the route.

Read the Plan and Section Together

A forklift enters through the side door, turns between two racks and lifts a pallet to the top level. Follow the orange line to the circle on A–A′ in the floor plan. The section shows the same spot from the side, including the pipe above the lift point.

Warehouse floor plan and forklift routeThe orange route enters through the left-hand door, turns between the racks and ends at the lift point on section line A–A′.RackRackForklift routeSide doorAA′Lift point
Floor planThe orange line shows the forklift route. Dark squares along the walls mark columns. This is a schematic. On your project plan, measure the narrowest gap between obstructions, including column faces and loads projecting beyond the racks. Compare it with the truck manufacturer’s aisle requirement for the model and load you intend to use.
Cross-section along A–A′A section through the lift point between two racks. The vertical arrow measures from the finished floor to the underside of the pipe above the forklift route.RackRackPipeClearheightFloor level
Section A–A′The arrow measures from the finished floor to the underside of the pipe at the lift point. Check how high both the load and the forklift mast will reach as the pallet is placed on the top rack. Allow for the clearance the operation requires.

What to ask the designer

“Could you overlay the columns on our rack layout and mark the narrowest point along the forklift route from the door to the racks? At the top-rack lift point, please show the height from the floor to the lowest obstruction so we can check it against our truck and load.”

What to Send With a Quote Request

Send every bidder the same drawing revision, site location, intended use, building dimensions and required clear height. Ask each to identify what the price includes, what costs extra and which assumptions need revisiting once you have better information.

ItemWhat to provideWhat to ask for
Clear spaceA layout showing machinery, racks, doors and forklift routes. Mark where trucks turn or lift a load.Ask for columns overlaid on the layout and a section showing clear height at the lift point. If the bidder proposes options with and without internal columns, request a price for each.
Equipment and future additionsDistinguish equipment required at opening from later additions, such as an overhead crane or rooftop solar panels. Mark their locations and attach available supplier data.Ask which equipment loads the design allows for. If it allows for solar panels, check whether the price also covers supplying and installing them.
Foundations and floor slabGive the required floor level, rack layout, load per pallet and machinery weights and locations. Share the same ground investigation report with each bidder if one is available.Request separate design and construction costs for the foundations and slab. Ask who will supply the column base reactions to the foundation engineer.
Delivery and erectionShow site access, laydown areas, space for a mobile crane and the hours when trucks can enter.Request prices for transport, unloading, crane hire and erection, or ask which sum covers them. Ask for the first delivery date and the erection completion date, with the drawing approval and site access dates they depend on.

Two Steel Connectionsto Check on the Drawings

Steel column base plate anchored to a concrete pedestal
Column base on concreteThe steel base plate sits beneath the column. The anchor rods and nuts are visible above the plate. Before concrete is poured, ask the foundation and steelwork teams to identify the rod positions on the same drawing and show how far the rods should project above the concrete.
Blue steel beam bolted to an industrial building column
Beam-to-column connectionFollow the blue beam to the grey column to see the end plate and rows of bolts. Ask the team to find this connection on the approved detail drawing, point out the plate and bolts, and identify who will inspect the work and record the result.

Compare Installed Steelwork Costs

These illustrative quotes are for the same warehouse, materials and erection scope. Each covers the steel frame, delivery and erection. Both exclude foundations, the floor slab, roof and wall cladding, and tax.

Quote A · Itemised

THB 1,440,000
Steel frame
THB 1,200,000
Delivery
THB 60,000
Erection
THB 180,000

Quote B · Lump sum

THB 1,400,000

One price covers the steel frame, delivery and erection.

For these three items, Quote B is THB 40,000 lower. Ask both bidders whether delivery includes unloading and whether erection includes crane hire. Add any separate charges to the relevant quote before comparing the total, completion date and warranty terms.

Drawing Approval and Handover

Before fabrication. Ask the fabricator and installer to confirm the approved drawing number and revision. If a door moves, a pipe route changes or a machine is replaced, mark the change and have the designer assess its structural implications. Before approving it, ask which parts will change and what that means for cost and delivery.

At handover. Walk the building with the site supervisor and compare it with the approved drawings. Check the columns and measure the narrowest point on the forklift route. Collect the as-built drawings, material list, inspection records required by the contract, maintenance instructions and warranties. If a coating is damaged, mark the location on the plan, take a photo and record who will fix it, the reinspection date and the outcome. If roofing is included, keep its warranty and leak-reporting contact with the handover records.

Questions Before Choosing a PEB

Can I request a budget price before choosing a forklift?

Yes. Send the loaded pallet dimensions, top rack level and proposed route. Ask the bidder to state the aisle width and clear height assumed in the price. Once you select a truck, have the designer check its loaded turning clearance and the height of both mast and load at the top rack before releasing the drawings for fabrication.

How should I compare prices per square metre?

Ask each bidder for the total price and the area used to calculate the rate. Does that area include only the warehouse floor, or also a mezzanine or space under a canopy? Check that the totals cover the same work, such as the frame, delivery and erection, and use the same tax basis. Compare the rates once both the area and scope match.

What should I tell the designer about future expansion?

Mark the direction of the extension, its approximate area and intended use. For example, you might extend the rear of the warehouse to add rack rows. Ask the designer to identify what the initial structure allows for and what will need further design. Before extending, have an engineer review the as-built drawings and current use.

Who checks the anchor rods when the foundations and steelwork are under separate contracts?

Name the inspector and the person responsible for the survey record in the scope of work. Before the pour, both teams should confirm the rod positions and levels on the same drawing revision. Before column erection, have the inspector measure the installed rod positions and elevations against the approved drawing and send the results to the installer. If a rod position or elevation differs from the drawing, have the designer assess it and confirm the remedy before erection.